Raipur | Correspondent: More than four months after the completion of paddy procurement operations in Chhattisgarh, over 10.76 lakh quintals of paddy are still lying at procurement centres across the state, raising serious concerns as the southwest monsoon approaches. Officials fear that if rainfall intensifies in the coming weeks, a substantial quantity of the stored grain could be damaged, resulting in significant financial losses.
According to official data, the paddy yet to be transported is valued at more than ₹333.74 crore at the minimum support price (MSP). Despite repeated extensions of the transportation deadline, authorities have failed to clear procurement centres before the onset of the rainy season.
The pending stock includes 7,48,310 quintals of coarse paddy, 1,21,020 quintals of fine paddy, and 2,07,250 quintals of Sarna variety paddy. Delays in lifting and transportation have once again exposed the state's procurement system to the risk of large-scale crop damage, a problem that has surfaced repeatedly in previous years.
Procurement Completed, But Transportation Lags Behind
During the 2025–26 procurement season, Chhattisgarh purchased a record 14.10 crore quintals of paddy from farmers. Out of this, 12.34 crore quintals were supplied to rice millers, while 1.65 crore quintals were transferred to storage centres.
Under procurement guidelines, all paddy should have been lifted from procurement centres by March 31. However, due to slow transportation and storage bottlenecks, the deadline was extended by two months until May 31. Even after the extension, a significant quantity remains stranded at procurement centres across the state.
With pre-monsoon showers already becoming active in several districts and weather forecasts predicting widespread rainfall over the coming days, concerns are growing that the exposed paddy stocks could deteriorate due to moisture, fungal growth, and prolonged exposure to adverse weather conditions.
Rajnandgaon: ₹17 Crore Worth of Paddy Yet to Be Lifted
The situation remains particularly worrying in Rajnandgaon district, where paddy lifting has remained incomplete in 79 out of 96 cooperative societies.
Officials said that nearly 56,000 quintals of paddy, worth approximately ₹17 crore, are still awaiting transportation. The district had procured around 62 lakh quintals of paddy under MSP operations by January 31, 2025. However, stocks have remained at procurement centres for nearly four months.
During this period, the paddy has faced multiple challenges. Continuous exposure to sunlight has caused drying and quality deterioration, while unseasonal rainfall has damaged portions of the stock through moisture absorption and spoilage.
Only a handful of centres located near urban areas, including Dhaba, Bhanpuri, Gathula, Sankara, Tumdibod, Khursitikul, Kolihapuri, Tendunala, Diwanbhedi and Kanharpuri-have reported complete lifting of their stocks. Many rural centres continue to struggle with pending transportation.
Bastar Division Faces Major Storage Challenge
The problem is even more severe in the Bastar division, where authorities had assigned 165 rice millers the responsibility of lifting procured paddy from procurement centres.
Although millers were initially instructed to complete transportation by March 31 and later given an extension until May 31, large quantities of grain still remain unattended. Official figures show that nearly 4.56 lakh quintals of paddy are lying at around 200 procurement centres across the division.
Purchased at an MSP of approximately ₹3,100 per quintal, the stock is valued at nearly ₹141 crore.
Rice millers have attributed the delay to a shortage of storage space in government warehouses as well as their own facilities. They also cited weather-related disruptions and logistical constraints as major reasons for the slow pace of lifting operations.
Risk of Financial Loss and Quality Deterioration
Agriculture experts warn that prolonged exposure to rain and humidity can significantly reduce the quality of paddy, affecting both milling recovery and market value. If the monsoon arrives in full force before the remaining stock is transported to safer storage facilities, the state could face losses running into hundreds of crores of rupees.
The situation has once again highlighted long-standing challenges in the procurement and transportation system, including inadequate storage infrastructure, dependence on millers for lifting operations, and delays in logistics management. Farmers' organizations and opposition leaders have urged the government to accelerate transportation efforts to prevent avoidable losses of public resources.
With weather conditions becoming increasingly unstable and monsoon activity expected to intensify in the coming weeks, officials are under pressure to ensure that the remaining paddy stocks are moved to secure storage facilities before heavy rainfall begins across the state.